Project: LPG Rail Expansion Project
Service: Complete Terminal and Tank Services
Location:Mont Belvieu, Texas
The project consisted on increasing the amount of LPG railcars unloaded per day from 30 to 60. Installed over 5400 feet of new rail, 20 new rail loading positions, 10 compressors, 2 fin fans, 1 chiller, four (4) 30,000-gallon ASME pressurized vessel, 3 charge pumps, and 3 pipeline pumps. Also, installed 4.60 miles of pipeline infrastructure to Enterprise facility. This project was contracted under R&R Drafting, Inc. Develop control logic for required permissive, shutdowns, and safeties from overpressure, no flow, vibration, etc. for the LPG Expansion project.